Ardenwood
bath

A primary bath remodel where the shower moved to the window wall. Drain relocated, thermostatic valve, rain head and hand shower, vanity across the room. Two weeks of plumbing inside a six-week remodel.

2 weeksplumbing, in two visits
6 weekswhole remodel
ArdenwoodFremont
A finished walk-in shower with stone tile, a rain head and a hand shower on a slide bar.
Finished shower · window wall

The job

Scope, days,
material.

Duration
Rough-in days 1–3, finish days 11–12
Moved
Shower drain, vanity supply and drain
Valve
Thermostatic, three outlets
Vent
New vent tied into the existing stack
Permit
Part of the contractor's remodel permit
Crew
One plumber, both visits

From the log

How the days went.

  1. Day 1

    Open

    Subfloor opened along the new drain path.

  2. Day 2

    Drains and vent

    Two-inch shower drain, vanity drain, vent tied in.

  3. Day 3

    Supply and valve

    Valve set to the tile plan. Rough-in inspected and passed.

  4. Day 11

    Trim

    Rain head, hand shower and vanity faucet set after tile.

  5. Day 12

    Test

    Every outlet run, drain flood-tested, handed back.

“The inspector said 'nice work' and left. That's never happened before.”

D. Alvarez, contractor

Like this one?
Walk us through yours.

Book a visit
Book a visit
Call (408) 555-0163 Book a visit

Claim this website for $0.

We build it free. Plans from $99/month after launch, cancel anytime.